Subscribe via RSS Feed Facebook page Connect with Eden DTC on Flickr

Storm Desmond in the EdenDTC catchments: 4th – 6th December 2015

Mary Ockenden, Lancaster University, Nick Barber, Newcastle University and Phil Haygarth, Lancaster University and members of the Eden DTC team

12 January 2016. pdf: Storm Desmond and Eden DTC3

Summary points:

  • The storm did not hit the Eden DTC catchments equally (rainfall – 156 mm at Newby Beck; 174 mm at Thackthwaite Beck; 55 mm at Pow Beck, which fell continuously for 34-37 hours)
  • Maximum discharge (accepting the uncertainty of rating curve when exceeded) was highest ever recorded by DTC at Thackthwaite Beck, nearly equal highest at Newby Beck and below the highest at Pow Beck
  • At all sites the duration of the storm was remarkable: e.g. at Newby Beck, discharge > 6 m3s-1 for 31 hours (c.f. maximum discharge on 22 Nov 2012 was higher, but > 6 m3s-1 for only 3.5 hours)
  • Sediment/Nutrient data is only available from Newby Beck. Event loads transferred during Storm Desmond were: sediment (84 tonnes); total phosphorus (TP) (194 kg); total reactive phosphorus (TRP) (78 kg); nitrate (8.9 tonnes). For sediment this was 12 – 22% of previously recorded annual loads; for nutrients 8 – 13% of annual load
  • Maximum and averaged concentrations of TP/TRP were lower than those recorded during some other storms (e,g, max. TP was 0.29 mg l-1 during Desmond compared to 0.84 mg l-1 during storm on 08 Nov 2015 or 1.0 mg l-1 on 22 Nov 2012)
  • The lower concentrations were attributed to the antecedent conditions during November – saturated ground and numerous smaller storms in quick succession, which may have flushed out the most readily mobilised sediment and nutrients. Nevertheless the duration of the storm and sustained high discharge ensured that loads exported were high.

The build up:

image001

For Desmond only:

Newby Beck Pow Beck Thackthwaite Beck
Rainfall start 04 Dec 2015 20:00 04 Dec 2015 19:00 04 Dec 2015 19:00
Rainfall end 06 Dec 2015 08:00 06 Dec 2015 05:00 06 Dec 2015 08:00
Rainfall duration 36 hours 34 hours 37 hours
Rainfall total 156 mm 55.2 mm 174 mm
Rainfall peak intensity 6.2 mm/hr 3.2 mm 8.7 mm/hr
Discharge start 04 Dec 2015 20:00 04 Dec 2015 19:00 04 Dec 2015 20:00
Discharge end 07 Dec 2015 08:00 07 Dec 2015 09:00 06 Dec 2015 20:00
Discharge duration 60 hours 62 hours 48 hours
Discharge total 83 mm 92 mm * 180 mm
Discharge peak 2.4 mm/hr 2.9 mm/hr * 7.7 mm/hr

*Discharge rating at Pow is no longer valid due to stream bed change

Newby Beck: Total rainfall:  156 mm

image003

Pow Beck: Total rainfall: 55.2 mm

 

image004

Thackthwaite Beck: Total rainfall: 174 mm

image005

For nutrients, the only data available is from Newby Beck:

Sediment (t) Total P (kg) Total Reactive P (kg) Nitrate (t)
Storm Desmond export 84 194 78 8.9
Annual export 380 – 680 1670 – 2320 650 – 920 68 – 94
% of annual 12 – 22 8 – 12 8 – 12 9 – 13
During Desmond: mg/l mg/l mg/l mg/l
Min Conc. 5* 0.062* 0.037* 7.2
Max Conc. 134 0.288 0.096 15.7*
Time averaged conc. 61 0.151 0.065 9.9
Flow weighted conc. 81 0.186 0.074 8.4

*Minimum concentrations of SS, TP, TRP and maximum nitrate were recorded at the beginning of the event (i.e. they represent initial values before response started)

For comparison, concentrations during the event on 8 November 2015 are given below (storm duration 20h compared with 60h for Storm Desmond)

During storm 8 Nov mg/l mg/l mg/l mg/l
Min Conc. 8 0.105 0.051 15.2
Max Conc. 439 0.842 0.178 23.6
Time averaged conc. 89 0.305 0.108 19.2
Flow weighted conc. 144 0.433 0.133 17.7
Total load 30 tonnes 78 kg 24 kg 3.2 tonnes

image006

image007

Using a linear event rainfall-event TP load relationship (as in Ockenden et al., 2016), we could predict the TP load at Pow for an event of 55.2 mm:

image008

Predicted load (including the uncertainty in the event rainfall – event load relationship) is 250 – 350 kg TP.

For Newby Beck, the measured TP load of Storm Desmond was lower than the linear relationship (based on events in 2011/12) suggested:

image009

However, the events in November may have resulted in flushing of P in November. Note the event on 9th November which resulted in the highest concentration of TP, TRP and SS recorded in November or December. Concentrations recorded in Storm Desmond were not as high, even at the start of the event when the highest concentrations are usually recorded. However, due to the long duration of the event (discharge > 5 m3 s-1 for 34 hours), the total loads were still large.

image010Storm Desmond and Eden DTC3

Reference:

Ockenden, M.C., Deasy, C.E., Benskin, C.M.H., Beven, K.J., Burke, S., Collins, A.J., Evans, R., Falloon, P.D., Forber, K.J., Hiscock, K.M., Hollaway, M.J., Kahana, R., Macleod, C.J.A., Reaney, S.M., Snell, M.A., Villamizar, M.L., Wearing, C., Withers, P.J.A., Zhou, J.G. and Haygarth, P.M., 2016. Changing climate and nutrient transfers: Evidence from high temporal resolution concentration-flow dynamics in headwater catchments. Science of the Total Environment http:\\dx.doi.org/10.1016.j.scitotenv.2015.12.086.

 

 

Tags: , ,

Category: Publications, Uncategorized

About the Author: Mary Ockenden works at Lancaster University of the NUTCAT project (http://nutcat2050.org.uk/). NUTCAT and EdenDTC are working together on diffuse pollution issues in the River Eden catchment

Comments are closed.